One way we can use the filter option and display the deadline dates but you won't be able to see the activities that impacting certain milestone. As you filter, it hides all other activities that not relevant.To define the schedule at Project level, create a start and finish milestone for each project and create a link between the two milestones.
1. Create WBS for your milestone
You might want to break your milestone into 2 categories
- Contractual Milestone ( Mechanical Completion, RFSU- Ready for Start-Up etc)
- Project Milestones ( PO date for long lead items, Site mobilization, piping tie-in completion and etc)
At this stage you can link respective milestone to the relevant activities by assigning SS (Start to start) or FF (Finish to Finish relationship).
The whole idea to have a glance on how the project milestone against the baseline rather than sifting through the whole project. This is convenient when comes to management review.