In an EPC project, Engineering progress usually measured by assigning a weight which are the number of required man-hours for each deliverable.
Once the task is deliverable is issued or approved, the corresponding man-hours are earned..In a typical project, engineering progress is measured as level 2 (phase) and level 3 (engineering discipline) and level 4 (document, RFQ, Datasheet and etc).
The progress calculation is done based on engineering work steps and their weight factors for an engineering drawing. See the below sample work steps and weight factors.
Engineering Progress Measurement by each different level
Manhours as an basis for Engineering Weightage.
An example of piping discipline tracking
Click here to Download : http://mbx.cm/t/vqLE-