How to manage Project Delay in Primavera P6


A subnet or fragnet is the best way to demonstrate a delay.In this method we will use fragnet to logically tie in to the network in order show the impact of changes to the schedule. This method also helps us to keep the historical data of the delays and grouping it with delay classification.

In my previous project, the EPC contractor planning team will sit with the client's team during the window analysis session in order to go through the events of delays. Good things about this practise is that both parties are aware of what is going on and work towards expediting the projects. After all EOT claim is an exhausting process for both team to go through.